South Africa

POWER CRISIS 

Koeberg’s Unit 1 back online, while Ramokgopa bemoans failure at Medupi and other units

Koeberg’s Unit 1 back online, while Ramokgopa bemoans failure  at Medupi and other units
Unit 1 at Koeberg nuclear power station is back on line after being overhauled as part of a process to extend its operating life by 20 years. (Photo: Dwayne Senior / Bloomberg via Getty Images)

The utility describes the successful synchronisation of Unit 1 at Koeberg to the grid as ‘a huge milestone in the generation and operational recovery plan’.  At the same time, Electricity Minister bemoans outages at six other power stations as a ‘major disappointment’.

After almost a year offline, Unit 1 at Koeberg power station has been successfully synchronised to the grid, Eskom announced on Saturday, 18 November. 

The outage at Unit 1 began on 10 December 2022 for the maintenance, refuelling and the replacement of three steam generators. Its return to service has been affected by delays. Most recently, in August, Daily Maverick reported that Eskom’s chief nuclear officer at Koeberg nuclear power plant, Keith Featherstone, said the unit was meant to return to service by 3 November. 

Read more in Daily Maverick: Koeberg power station’s Unit 1 set to be finally back online by November — Eskom

In Saturday’s media release, Eskom said the synchronisation came “after almost a year and the longest outage in the history of the station, during which the original three steam generators were successfully replaced by three new steam generators”. 

It was “a huge milestone in the generation operational recovery plan and Eskom’s strategic objectives”, the utility said. 

Eskom group executive for generation, Bheki Nxumalo, said: “This milestone is a result of the hard work and determination of the Eskom employees, suppliers and contractors who have had to endure a long and challenging outage in the Koeberg power station’s history.” 

Koeberg – situated in the Western Cape – is the country’s only nuclear power station, with a total generation capacity of 1,860MW, about 5 % of Eskom’s total generation capacity. 

Read more in Daily Maverick: Further delay in life extension of Koeberg nuclear reactor worsens power outlook

Unit 2 outage

Eskom said for the duration of the outage at Unit, Unit 2 had been safely generating electricity into the grid. It will continue to do so until the start of its next outage, which will include the replacement of its three original steam generators. Unit 2 will be shut down for refuelling, maintenance and replacement, similar to the outage at Unit 1. 

“Although Unit 2 outage will be similar in terms of the scope, the lessons learnt from Unit 1 outage will enable the duration to be reduced; however, as was the case during the Unit 1 outage, nuclear safety will not be compromised,” Eskom said. 

According to Eskom, the replacement of the steam generators is a huge milestone in the life of Koeberg, as it was identified by Eskom as a “prerequisite”for the extension of the operating licence for Koeberg. 

It is part of the process to extend Koeberg’s original design life of 40 years. Eskom says the National Nuclear Regulator is already evaluating a licence application from Koeberg to extend its operating life by 20 years.

According to energy expert Chris Yelland, if an application for Unit 2’s extended expiry date is not granted, then it is possible that both units may have to shut down on 21 July 2024.

‘Significant failure’

Meanwhile, in his weekly briefing on Sunday morning, Minister in the Presidency responsible for Electricity, Kgosientsho Ramokgopa, said unplanned grid losses in the past two weeks were a “major disappointment”. In the weeks before, there had been no scheduled power cuts. 

Ramokgopa said there was a “significant failure of a cluster of units” at Eskom, including at Medupi, Camden, Duvha, Lethabo, Kriel and Hendriena. The unit offline at Medupi was “a really big unit”, he said. 

Ramokgopa said the failure caused a loss of 2,000MW, which was “just shy of three stages” of scheduled power cuts. 

He said five units should come back online by midnight and the others should come back tomorrow. DM

Gallery

Comments - Please in order to comment.

  • Mike Newton says:

    Maintaining a coal fired power station is not rocket science. Most of these stations have years of history. This makes it possible to schedule maintenance ahead of failures. Similarly operating procedures will have been honed over the years. If procedures are followed an on line time of over 90% outside scheduled maintenance is a reasonable goal.

Please peer review 3 community comments before your comment can be posted

X

This article is free to read.

Sign up for free or sign in to continue reading.

Unlike our competitors, we don’t force you to pay to read the news but we do need your email address to make your experience better.


Nearly there! Create a password to finish signing up with us:

Please enter your password or get a sign in link if you’ve forgotten

Open Sesame! Thanks for signing up.

We would like our readers to start paying for Daily Maverick...

…but we are not going to force you to. Over 10 million users come to us each month for the news. We have not put it behind a paywall because the truth should not be a luxury.

Instead we ask our readers who can afford to contribute, even a small amount each month, to do so.

If you appreciate it and want to see us keep going then please consider contributing whatever you can.

Support Daily Maverick→
Payment options

Premier Debate: Gauten Edition Banner

Join the Gauteng Premier Debate.

On 9 May 2024, The Forum in Bryanston will transform into a battleground for visions, solutions and, dare we say, some spicy debates as we launch the inaugural Daily Maverick Debates series.

We’re talking about the top premier candidates from Gauteng debating as they battle it out for your attention and, ultimately, your vote.

Daily Maverick Elections Toolbox

Feeling powerless in politics?

Equip yourself with the tools you need for an informed decision this election. Get the Elections Toolbox with shareable party manifesto guide.