Koeberg nuclear plant life extension difficulties — SA’s  nuclear sector has failed its test

Koeberg nuclear plant life extension difficulties — SA’s  nuclear sector has failed its test
Beachgoers walk in front of the Koeberg power facility in Cape Town, South Africa 21 January 2011. Koeberg power station is the only nuclear power station on the African continent. It is situated at Melkbos, 30km northwest of Cape Town. (Photo: EPA/Nic Bothma)

Some civil society groups have called for the closure of Koeberg when its current licence expires in 2024. South Africa’s extreme electricity crisis would make such a closure very difficult to absorb.

South Africa’s only nuclear power plant, Koeberg, has frequently been in the news in 2022, all for the wrong reasons.

Its operating licence expires in 2024, and its continued operation thereafter depends on critical refurbishments and upgrades. Work on these finally began in January this year, but immediately ran into difficulties, forcing significant delays.

Koeberg is supplying only half of its power while work is in progress. This has amplified the crippling power shortages South Africa has been experiencing. This state of affairs, where the country effectively has 3% less generating power available than it would otherwise have, is expected to persist for the bulk of the next two years.

Other potential signs of turbulence linked to Koeberg include:

  • the delayed application to the nuclear regulator to extend the plant’s licence;
  • the controversial dismissal of one of the regulator’s board members — an opponent of nuclear power — by the Minister of Mineral and Energy Resources; and
  • resignations of senior Koeberg staff, though there is no evidence that these were due to friction.

All of this has led to speculation that the Koeberg life extension exercise is in difficulty. In turn, it casts doubt on the capacity of South Africa’s nuclear sector, and is likely to put to bed the highly ambitious proposals still advocated within the sector to build new nuclear plants.

Koeberg’s history

Koeberg, Africa’s only operational nuclear power station, 27km north of the Cape Town city centre, is reaching the end of its scheduled life cycle.

The plant consists of two units of just over 900 megawatts each, and together these contribute roughly 5% of South Africa’s electricity.

Koeberg was built by the French company Framatome between 1978 and 1984. In line with international practice, the plant was granted a 40-year operational licence which will expire in July 2024. Licensing the plant for a further 20 years is possible, as long as it meets specific safety criteria. Typically these involve particular upgrades and the replacement of various components.

So far the plant has operated reasonably safely, with only comparatively minor incidents recorded.


Visit Daily Maverick’s home page for more news, analysis and investigations


Some civil society groups have called for the closure of Koeberg when its current licence expires in 2024. South Africa’s extreme electricity crisis would make such a closure very difficult to absorb. While the construction of new nuclear plants is prohibitively expensive and very time intensive, extending the life span of an existing plant is in principle achievable in the short term and financially defensible.

The extension of the lifespan of Koeberg was also envisaged in the government-endorsed 2019 Integrated Resource Plan for electricity.

Nuclear activities in South Africa are controlled by the National Nuclear Regulator. The regulator is expected to be guided by recommendations drawn up by experts commissioned by the International Atomic Energy Agency who inspected Koeberg in 2019. These recommendations include technical interventions for operating the plant safely for another 20 years. The most significant of these is the replacement of steam generators.

The upgrade is projected to cost R20-billion ($1.2 -billion). Most of this would go towards buying and installing six new steam generators.

The need to replace them was identified over 10 years ago, but protracted litigation over who would do the job held up the project. The operation was eventually scheduled for 2022.

Life extension project

The replacements and upgrades needed to secure a 20-year operating licence extension require each Koeberg unit to be shut down for a projected five months. Unit 2 was therefore switched off on 18 January 2022 and was supposed to reopen in June 2022. Unit 1 was then to go through the same process, starting in October.

Things then went wrong. The critical steam generator replacement was again postponed to 2023. The full reasons have not been officially disclosed. But there has been no denial of reports that the onsite storage facilities for the now radioactively contaminated old steam generators were not ready.

The delay in getting Koeberg Unit 2 up and running on schedule resulted in an additional 900 MW shortfall during South Africa’s most recent midwinter bout of severe power blackouts.

Unit 2 finally started operating again on 7 August, almost two months later than projected. Another outage of comparable duration is still required in 2023.

Significance for the nuclear sector

The mishandling of the Koeberg life extension project raises serious questions about the capacity of South Africa’s nuclear sector. This sector has advocated the building of a large fleet of new nuclear plants, implying that it could be done without major cost and time overruns. But the much smaller and far more straightforward Koeberg upgrade has not gone well.

South Africa should drop any ambitions for new nuclear plants. The nuclear sector should instead focus on its more modest target, namely to complete the Koeberg upgrade, run the plant for another 20 years and then complete the potentially problematic decommissioning. DM

Hartmut Winkler is Professor of Physics at University of Johannesburg.

First published by The Conversation.

Gallery
Absa OBP

Comments - Please in order to comment.

  • Marthinus Wolhuter says:

    Dear Professor Winkler, the South African nuclear sector is no more. Skilled nuclear staff has been head-hunted by international research institutes, utility companies and equipment manufacturers since 2008 at least.
    Since then the nuclear safety culture in SA has also dribbled down the drain!
    Now that the 6th steam generator had been dropped on the deck by the manufacturer in China, it will have to be scrapped and remanufactured. Now there is no way that Eskom can complete the required replacement of the steam generators before the current operating licence expires.
    The site of the Koeberg Nuclear Power Station was not properly thought through when it was planned in the 1970’s. The salt spray from the ocean is causing major corrosion issues on the site like spalling of concrete reinforcement.
    Urban development also encroached the site. With KNPS being just 30 km away from Cape Town’s city centre, the city and all the residential area in between will be in the contamination zone of even a small release of nuclear material. Nowadays the exclusion zone in case of a major accident like the meltdown of a reactor core or similar accident (like Fukushima) is 50 km radius and safety zone 200 km radius.
    In the event of a major nuclear accident at KNPS the whole Cape Peninsula will be nuclear wasteland, uninhabitable for thousands of years!
    I suggest Eskom cut their losses and decommission KNPS in 2024 at the end of its design life.
    Rather focus on renewable energy. Let nuclear go!

Please peer review 3 community comments before your comment can be posted

We would like our readers to start paying for Daily Maverick...

…but we are not going to force you to. Over 10 million users come to us each month for the news. We have not put it behind a paywall because the truth should not be a luxury.

Instead we ask our readers who can afford to contribute, even a small amount each month, to do so.

If you appreciate it and want to see us keep going then please consider contributing whatever you can.

Support Daily Maverick→
Payment options