Sewage in the sea — City marine outfall discharge falls foul of Hout Bay permit conditions

Sewage in the sea — City marine outfall discharge falls foul of Hout Bay permit conditions
More sewage than allowed has been pumped into the sea at Hout Bay. (Photo: Steve Kretzmann)

The City of Cape Town’s own data shows it is releasing more sewage than it is allowed.

The City of Cape Town has been pumping more sewage into the ocean at Hout Bay than is allowed, the City’s own data reveals. And the sewage does not meet the minimum standards for effluent discharge.

Raw sewage from Hout Bay is pushed through a three millimetre grid to remove solids, and then pumped through a pipe that extends 1.7km out to sea at a depth of 37 metres. This is one of three such marine sewage outfalls in Cape Town, the other two being at Green Point and Camps Bay.

The permit for the release of sewage through the Hout Bay marine outfall was granted by Minister of Forestry, Fisheries and the Environment (DFFE) Barbara Creecy in 2019. Permits for the Green Point and Camps Bay outfalls were granted in December 2022 and January 2023 respectively. Creecy has since ordered the City to undertake a public participation process in relation to the issuing of the permits. The public participation process ends on 21 November.

But according to information from the City obtained via a Promotion of Access to Information Act (Paia) application by ActionSA provincial chairperson Michelle Wasserman, the City has been violating special conditions included in the marine outfall discharge permit for Hout Bay.

ActionSA has now laid a criminal charge for violation of the Integrated Coastal Management Act.

The data and documents obtained by Wasserman show that the City pumped more than the maximum allowed volume of five million litres of sewage per day from the outfall on 104 out of 181 days in the first six months of this year. On six of these days, the City released more than double the allowed maximum volume of sewage into the ocean, releasing as much as 12.5-million litres in one day. The pipe is designed to manage a maximum of 9.6-million litres a day.

Over the six-month period, the City released over one billion litres of sewage through the Hout Bay outfall. At five million litres a day, the maximum allowed flow for the period is 905-million litres.

According to the permit conditions, the maximum allowed volume must not be exceeded without authorisation from the DFFE. Wasserman says the City told her “no authorisation was received”.

The data provided by the City also shows that sewage quality did not meet minimum standards.

Levels were exceeded for the amount of suspended solids in the sewage effluent, the chemical oxygen demand, and the pH. On some days these levels were not even measured. No results were provided for the levels of arsenic, cadmium, calcium, copper, chromium, cyanide, or mercury, all of which are supposed to be measured weekly.

Read more in Daily Maverick: Barbara Creecy chides City of Cape Town over ‘inadequate’ public engagement on sewage pumped into sea

The permit granted by the DFFE in 2019 stipulates that the City must set up or join a Permit Advisory Forum within six months of the permit being granted. The forum must meet at least four times a year to discuss any breaches of the permit conditions, monitoring and reporting requirements, and any general issues related to the outfall. But in response to Wasserman’s Paia request for information on this issue, the City responded with an incomplete sentence: “The City of Cape Town has previously reached out to.” (sic)

“From the City of Cape Town’s response, it is clear that this important oversight body required by the Permit was never established,” stated Wasserman in her affidavit to the police submitted on 2 November.

Wasserman notes in her affidavit that the City’s failure to comply with the conditions of the outfall discharge permit means it falls foul of the Integrated Coastal Management Act of 2008. She has asked the police to investigate the contravention of the Act.

Wasserman said she did not submit a Paia request for the monitoring results of the Green Point and Camps Bay outfalls as the permits for these were only issued in December 2022 and January 2023, so a significant amount of data from monitoring would not yet have been collected.

City responds

City water and sanitation mayco member Zahid Badroodien said, “The City continues to operate the marine outfalls with current permits and licence conditions as issued by the Department of Water and Sanitation/DFFE.”

Badroodien said the City welcomed Minister Creecy’s determination that the City should conduct a public participation process on the granting of permits for the three marine outfalls in the city.

He said the City has also commissioned a study to determine the feasibility and cost of treating the sewage before releasing it into the ocean, or alternatively, pumping it to existing sewage treatment works. A draft scoping report for the study is under review, he said, and once the report was finalised there would be further community engagements regarding the outfalls. DM

First published by GroundUp.

Gallery
Absa OBP

Comments - Please in order to comment.

  • Mark Jackson says:

    This article is incorrect in that it states the pipeline extends 1.7km out to sea. In fact, if one enters the pumps station co-ordinates, and pipeline discharge co-ordinates into Google Earth, one will see that the discharge point is only 1020m from the pumping station, and only 700m form the nearest shore. (These co-ordinates are available on the outfall permit)

  • Wacky Me says:

    ……and the DA wants my vote? Shocking

  • Denise Smit says:

    Action SA looks for things to do. They should tackle the true issues bringing down SA and the future of the country like the ANC/EFF corruption and failed management. Wasserman and company do not have the stomach to do so, they go for small fish.

  • Geoff Hainebach Hainebach says:

    How many of those people who wrote the article and the comments that followed have read the detailed report done by the CSIR. It is difficult for laymen to understand but one would easily realise that the matter is much more complicated than appears from the article.

    • David Peddle says:

      Possibly you could explain what the CSIR report entails as in common with the great unwashed masses, I have no idea what it contains

    • Mark Jackson says:

      I am familiar with the 2017 CSIR report – in fact I interview the CSIR after the city finally released it, 5 months after the CSIR finished it. And guess what. a) The city curtailed the scope of the report, from what the CSIR originally proposed, and b) the city supplied a lot of the data for that report. So it is in no ways an independent report, but rather a joint-city-CSIR report!
      The authors even acknowledge the limited scope of the report by saying: “.“This does not mean there are no ecological impacts and human health risks associated with this practice, but rather that no major ecological impacts could be detected through the monitoring approach followed in this study.”
      Emphasis on ‘in this study’…

  • Rob Fisher says:

    Pumping raw sewerage into the sea is bad.
    Letting raw sewerage run into rivers is so much worse.
    Let the ANC take the log out of their council’s eye first.

Please peer review 3 community comments before your comment can be posted

We would like our readers to start paying for Daily Maverick...

…but we are not going to force you to. Over 10 million users come to us each month for the news. We have not put it behind a paywall because the truth should not be a luxury.

Instead we ask our readers who can afford to contribute, even a small amount each month, to do so.

If you appreciate it and want to see us keep going then please consider contributing whatever you can.

Support Daily Maverick→
Payment options

Premier Debate: Gauten Edition Banner

Gauteng! Brace yourselves for The Premier Debate!

How will elected officials deal with Gauteng’s myriad problems of crime, unemployment, water supply, infrastructure collapse and potentially working in a coalition?

Come find out at the inaugural Daily Maverick Debate where Stephen Grootes will hold no punches in putting the hard questions to Gauteng’s premier candidates, on 9 May 2024 at The Forum at The Campus, Bryanston.