South Africa

South Africa

Eskom’s boiler contractor at Medupi and Kusile defends its reputation

Eskom’s boiler contractor at Medupi and Kusile defends its reputation

Eskom’s boiler works contractor at Medupi and Kusile has moved to defend its reputation, and to clarify its position in respect of any perceived non-performances in meeting its contractual obligations to deliver steam of the right cleanliness, speed, temperature, pressure and mass flow-rate to the turbines at the power station construction sites. By CHRIS YELLAND.

At a briefing on 23 January 2015, David Milner, responsible for business development and corporate communications at Mitsubishi Hitachi Power Systems Africa (MHPSA) (formerly known as Hitachi Power Africa), refuted any suggestions that the company had incorrectly designed the temporary pipework for blow-through testing at Medupi.

On the contrary, Milner indicated that the temporary pipework for blow-through testing had been correctly designed to meet the steam conditions specified by Eskom for blow-through testing of both the high pressure and intermediate pressure pipework systems of Unit 6 at Medupi (the first unit to be commissioned).

Milner also gave the assurance that, for the high-pressure system, the required levels of steam cleanliness, as measured by the number and diameter of indentations in a defined area on a target plate installed in the temporary blow-through piping, met the contractual requirements specified by Eskom in its contract with MHPSA. He said the company was on the way to achieving these requirements on the intermediate pressure system when the blow-through testing was stopped by Eskom.

Steam blow-through is conducted after chemical cleaning to blow steam through the boiler and associated pipework in order to clean the plant of construction debris, particles, scale and other contaminants, and establish and prove the required steam inlet conditions before connecting the final piping to the steam valve and turbine. Eskom contractual specifications set out the required steam speed, steam turbulence factor and steam mass flow-rate to be used during the blow-through process, where conditions are far more severe than during normal full-load operation. MHPSA says it met all such contractual requirements on the high pressure system.

It would appear that the problems reported by Eskom in achieving the required levels of steam cleanliness at the specified steam speed, turbulence and flow rate conditions during blow-through testing are the result of some “disconnect” between Eskom’s contractual specifications with its boiler works contractor (MHPSA) and its turbine works contractor (Alstom).

Part of this disconnect relates to the actual point of measurement of steam speed, with MHPSA indicating that its contract with Eskom clearly states this should be at the target plate within the steam pipe, where the pipe cross-sectional area is somewhat reduced due to the target plate itself. MHSPA says that if the steam speed is measured at a position away from the target plate, where the pipe cross-sectional area is greater, the steam speed would be lower. The measurement procedure used, says MHPA, was not in accordance with its contract with Eskom.

MHPSA says that, at the target plate, the steam speed was above the 200 meters per second required in its contract with Eskom. Measured elsewhere in the pipe, the steam speed would have been around 180 metres per second, and this is what has led to public confusion around the issue.

A further disconnect between the boiler and turbine steam quality specifications relates to the way in which the steam contaminant particle size diameter is calculated from indentations in the target plate after blow-through. As a result of particles striking the target plate at various angles, some indentations are elliptical and not circular, and in these cases MHPSA suggests that various methods can be used to calculate the contaminant particle sizes in the steam during blow-through testing.

The final area of confusion between the boiler and turbine steam quality specifications relates to the area size on the target plate within which a count is done on the number of contaminant indentations after blow-through testing. The area size is specified in MHPSA’s contract, but a larger target plate area for the count would obviously affect the number of indentations measured.

While the issues detailed above are indeed somewhat technical and obscure, the outcome of the delays in completion and contractual acceptance of the blow-through test results have already caused significant additional fuel oil costs to fire the boiler during the extended blow-through testing period. The 7- to 9-week delay in first synchronisation of Unit 6 at Medupi, due to the extended blow-through and other issues not related to MHPSA, could also result in additional open cycle gas turbine (OCGT) diesel costs being incurred by Eskom. Eskom has indicated that it spends R1- to R2-billion per month on diesel to run the OCGTs in the Western Cape.

Mitsubishi Hitachi Power Systems Africa, based in Johannesburg, recently announced management changes in which Eitaro Takayama was appointed executive chairman and Toshinori Shigenaka CEO on 1 December 2014. Hirosumi Sometani becomes chief commercial officer, while Shiro Ishise becomes executive director, projects.

The changes were announced by Takato Nishizawa, president and CEO of the Japanese parent company, Mitsubishi Hitachi Power Systems, and reflect an increased role within the South African operation by its Japanese management and technical staff. The company was formed in February 2014, integrating the global thermal power generation systems businesses of Mitsubishi Heavy Industries (MHI) and Hitachi.

The new South African subsidiary, Mitsubishi Hitachi Power Systems Africa, is part of the merged Mitsubishi/Hitachi entity, and took over the Medupi and Kusile boiler contracts awarded to Hitachi Power Africa. Mitsubishi Hitachi Power Systems Japan became the majority shareholder in the South African operation in October 2014, acquiring the 75% shareholding previously held by Mitsubishi Hitachi Power Systems Europe. The remaining 25% is held by a Black Economic Empowerment (BEE) partner, Kagosano NPC, a special purpose BEE vehicle set up to replace the 25% financial interest in Hitachi Power Africa formerly held by ANC investment company, Chancellor House. DM

Photo: Medupi Boiler Units 6, 5 and 4 as at June 2012 ( Mitsubishi Hitachi Power Systems Africa)

Gallery

Please peer review 3 community comments before your comment can be posted

X

This article is free to read.

Sign up for free or sign in to continue reading.

Unlike our competitors, we don’t force you to pay to read the news but we do need your email address to make your experience better.


Nearly there! Create a password to finish signing up with us:

Please enter your password or get a sign in link if you’ve forgotten

Open Sesame! Thanks for signing up.

We would like our readers to start paying for Daily Maverick...

…but we are not going to force you to. Over 10 million users come to us each month for the news. We have not put it behind a paywall because the truth should not be a luxury.

Instead we ask our readers who can afford to contribute, even a small amount each month, to do so.

If you appreciate it and want to see us keep going then please consider contributing whatever you can.

Support Daily Maverick→
Payment options

Daily Maverick Elections Toolbox

Feeling powerless in politics?

Equip yourself with the tools you need for an informed decision this election. Get the Elections Toolbox with shareable party manifesto guide.