An impression of the proposed River Club development contained in the Basic Assessment Report, a public document produced by SRK Consulting.

In this right of reply, the developers of a controversial development proposal in Observatory, Cape Town, say an appeal ruling by Heritage Western Cape is effectively moot and the decision rests now the Western Cape Government’s Department of Environmental Affairs and Development Planning.

The article Victory for First Nation peoples as R4bn River Club development is halted (Daily Maverick, 15 April 2020) contains serious inaccuracies that need to be corrected.

First of all, the proposed River Club project – a mixed-use, mixed income development in Observatory that will create over 6,000 jobs and attract international investment – has not, in fact, been halted.

The Heritage Appeal Tribunal ruling reported on in the article has no material impact on the progress of the development whatsoever. The tribunal simply dismissed our appeal – lodged two years ago – against a provisional protection order that Heritage Western Cape (HWC) had placed over the site in 2018.

We had lodged an appeal against the provisional protection order for the lack of procedural fairness of HWC’s decision to provisionally protect the River Club site.

However, in any event, that provisional protection order lapsed on Monday 20 April – six days after the Tribunal’s ruling. This effectively renders the tribunal’s ruling moot, since the protection order is now lifted anyway.

So, the development has certainly not been halted. On the contrary, a Basic Assessment Report, which includes a comprehensive and independent Heritage Impact Assessment, has been submitted to the Western Cape Government’s Department of Environmental Affairs and Development Planning for their final consideration and decision. The Basic Assessment Report was compiled after extensive public participation and expert consultation.

Second, we believe it is not true – as the article suggests – that halting the development would be a victory for the First Nation’s people. Indeed, the project enjoys the support of the majority of First Nations leaders historically located in the area of the site. 

There have been extensive, transparent and constructive public engagements with all interested and affected parties including the majority of Khoi and San mandated leaders, known as the First Nations Collective. This includes the Gorinhaiqua, Cochoqua, Gorachouqua and the San First Nation groups who used to historically settle on the River Club and Two Rivers land.

Based on these engagements, the First Nations Collective has expressed its full and unequivocal support for the River Club redevelopment both publicly and directly before HWC. In essence, the collective recognises that the proposed project will provide opportunities to reclaim, share and celebrate First Nations heritage with the public.

The proposed development embodies fundamental First Nations heritage elements that include:

  •   The establishment of a First Nations Cultural, Heritage and Media centre on the site; 
  •   An Indigenous Garden for medicinal plants used by the First Nations; 
  •   A Heritage Ecotrail that goes around the site; 
  •   An amphitheatre to showcase cultural performances by both the First Nations and the general public.

Furthermore, the history of the First Nations in the area will be visually commemorated by incorporating various symbols central to the First Nations narrative in the designs of the buildings throughout the development.

The Heritage Appeal Tribunal Committee was aware that all of these key heritage components were included in the information submitted to HWC as part of the Heritage Impact Assessment. This was also presented on numerous occasions by the First Nations Collective who were in attendance at the Appeal Tribunal and confirmed their support for the development. Inexplicably, the tribunal appears to have completely ignored this.

Instead, the tribunal appears to have been used for political purposes. Despite every effort to engage other First Nations groupings not historically located at the River Club land, through the Heritage Impact Assessment public participation process, these other groups elected on their own, not to engage. Instead, they used the appeal tribunal as a vocal political platform to voice objection.

Aside from the substantive heritage considerations, the tribunal’s finding also appears to have ignored decided case law and legal precedent. Suffice it to say, we do not agree with the tribunal’s ruling and our legal counsel’s considered view is that it would not survive scrutiny on judicial review. But given that the provisional protection order expired on 20 April 2020, this falls away.

We will, therefore, continue to progress our application via the correct channels. The recession the country faces – now amplified by the Covid-19 crisis – highlights the urgent need for responsible and inclusive socio-economic development and the proposed R4-billion River Club redevelopment is exactly that.

This project will create thousands of vital jobs on private land that is centrally located but severely underutilised. The project will also offer vital socio-economic benefits including an accessible school, inclusive housing, major upgrades to surrounding road infrastructure and public transport facilities, rehabilitation of the riverine corridor, and dedicated safe recreational spaces that will be open to the public.

The Liesbeek Leisure Properties Trust remains committed to working with all stakeholders to create a more inclusive and sustainable city and province. DM

Gallery

Please peer review 3 community comments before your comment can be posted

X

This article is free to read.

Sign up for free or sign in to continue reading.

Unlike our competitors, we don’t force you to pay to read the news but we do need your email address to make your experience better.


Nearly there! Create a password to finish signing up with us:

Please enter your password or get a sign in link if you’ve forgotten

Open Sesame! Thanks for signing up.

We would like our readers to start paying for Daily Maverick...

…but we are not going to force you to. Over 10 million users come to us each month for the news. We have not put it behind a paywall because the truth should not be a luxury.

Instead we ask our readers who can afford to contribute, even a small amount each month, to do so.

If you appreciate it and want to see us keep going then please consider contributing whatever you can.

Support Daily Maverick→
Payment options