title: "City moves to appoint managing agent for the Johannesburg Transport Interchange Centre"
description: "Ten years after construction began, the tender to appoint an agent to operate and manage the Johannesburg Transport Interchange Centre is ‘in process’ and expected to be finalised within three months."
type: "NewsArticle"
publisher: "Daily Maverick"
site: "https://www.dailymaverick.co.za"
section: "OUR CITY NEWS"
author: "Karabelo Phakoe"
author_url: "https://www.dailymaverick.co.za/author/karabelo-phakoe/"
canonical_url: "https://www.dailymaverick.co.za/article/2026-03-08-city-moves-to-appoint-managing-agent-forr-the-johannesburg-transport-interchange/"
published: "2026-03-08T12:34:30"
lang: "en-ZA"
word_count: 430
---

# City moves to appoint managing agent for the Johannesburg Transport Interchange Centre

> Ten years after construction began, the tender to appoint an agent to operate and manage the Johannesburg Transport Interchange Centre is ‘in process’ and expected to be finalised within three months.

By Karabelo Phakoe · Published 8 March 2026, 14:34 SAST

## Key points
- The City of Johannesburg is moving to appoint a managing agent for the Johannesburg Transport Interchange Centre, a facility completed in 2021 after a R516-million investment.
- Despite construction beginning in 2016, the centre has yet to operate due to delays attributed to stakeholder engagement and user verification processes.
- A recent tender briefing aims to expedite operations, with hopes to have the centre functional by the first quarter of the city’s new financial year.
- Security concerns have been addressed following illegal occupations of the building, but the City remains optimistic that the long-awaited facility will soon open its doors.

## Content

The City of Johannesburg has initiated a process to appoint a managing agent for the troubled Johannesburg Transport Interchange (JITI) Centre, which was completed in 2021 at a cost of R516-million.

The City held a tender briefing session on Tuesday, 3 March 2026 and said it wants to move faster to operationalise the delayed facility.

The centre was meant to be a central public transport hub with a terminal for cross-border buses, space for a taxi rank and parking. Construction started in 2016, but 10 years later the centre has yet to operate.

Responding to questions about the delay, Benny Makgoga, director of marketing and communications in the transport department, said the delay was due to “comprehensive stakeholder engagement that included the verification process of potential users of the facility”.

The verification process was now at an advanced stage.

The tender briefing session formed part of the City’s plan to appoint a managing or facility agent responsible for operations and management of the centre, he said.

The envisaged contract would run for nine years and 11 months. Makgoga clarified that the briefing was specifically to oversee the operational functioning of the facility.

“The tender to appoint a managing agent to operate and manage JITI is in process and it is anticipated to be finalised within three months. The centre is expected to be operationalised in the first quarter of the City’s new financial year,” he said.

While the project was initially positioned as a catalyst for job creation and skills development for residents of Johannesburg, Makgoga said 32 temporary jobs were created during the construction phase, with 18 small, medium and micro enterprise companies appointed for various opportunities.

![OCN-JITI-agent](https://cdn.dailymaverick.co.za/i/X3AKwiiAnM-zBQC9ojxzeFl2bhs=/200x100/smart/filters:strip_exif\(\)/file/attachments/orphans/JITI_building_23a_599195.jpg)

*People attend a tender briefing at the JITI building in Newtown on 3 March 2026. (Photo: Our City News / James Oatway)*

Police raided the building a few months ago, removing illegal occupants and informal traders, including some who were using the building as breeding ground for broiler chickens.

The City also confirmed that there had been minor vandalism at the building during the period it was informally occupied, but security has since been improved.

![OCN-JITI-agent MAIN1](https://cdn.dailymaverick.co.za/i/dxuzUpm_lhmegt95Iy5vKED_Whw=/200x100/smart/filters:strip_exif\(\)/file/attachments/orphans/JITI_building_13a_384836.jpg)

*Contractors inspect the JITI building on 3 March 2026. (Photo: Our City News / James Oatway)*

“No delays are expected,” Makgoga said, adding that the City would make sure that the facility was operationalised.

With the managing agent tender under way, attention turns to whether the long-anticipated facility will finally open its doors after several years of delay. **DM**

*This story is produced by [Our City News](https://ourcitynews.co.za/), a nonprofit newsroom that serves the people of Johannesburg.*