title: "Dean Macpherson - Telkom Towers police HQ a 'monument to inefficient management', with 80% of projects delayed"
description: "A billion rand later, the department will either repurpose the complex or get rid of it"
type: "NewsArticle"
publisher: "Daily Maverick"
site: "https://www.dailymaverick.co.za"
section: "GROUNDUP"
author: "Matthew Hirsch"
author_url: "https://www.dailymaverick.co.za/author/matthew-hirsch/"
canonical_url: "https://www.dailymaverick.co.za/article/2024-11-15-dean-macpherson-telkom-towers-police-hq-a-monument-to-inefficient-management-with-80-of-projects-delayed/"
published: "2024-11-15T14:31:40"
updated: "2024-11-15T14:31:43"
lang: "en-ZA"
word_count: 433
---

# Dean Macpherson - Telkom Towers police HQ a 'monument to inefficient management', with 80% of projects delayed

> A billion rand later, the department will either repurpose the complex or get rid of it

By Matthew Hirsch · Published 15 November 2024, 16:31 SAST · Updated 15 November 2024, 16:31 SAST

## Key points
- In a stunning display of bureaucratic ballet, Minister Dean Macpherson revealed that nearly 80% of public works projects are stuck in limbo, with the Telkom Towers complex standing tall as a monument to mismanagement, wasted cash, and the unfulfilled dreams of a nation.
- Public Works Minister Dean Macpherson reports that nearly 80% of public works projects are delayed, exemplified by the troubled Telkom Towers complex.
- The complex, purchased for R700-million in 2016, has been declared unfit for habitation and has cost R1-billion in upgrades over the past decade.
- An oversight report highlights numerous safety issues at the site, with only one of nine buildings occupied by SAPS, while excessive private lease payments continue.
- Macpherson vows accountability for contractors and is considering repurposing or divesting the complex, as delays in 164 out of 206 projects cost nearly R3-billion.

## Content

Public Works and Infrastructure Minister Dean Macpherson revealed on Thursday in Parliament that nearly 80% of public works projects are currently delayed, and the troubled Telkom Towers complex in Pretoria is a prime example.![Image](https://republish.groundup.org.za/counter/hit/14785/public-works-minister-telkom-towers-police-hq-a-monument-to-inefficient-management/)

The complex, purchased for R700-million in 2016 to serve as the South African Police Service (SAPS) headquarters, [was evacuated](https://groundup.org.za/article/auditor-general-tells-mps-of-damning-report-on-saps-headquater/) in February after being declared unfit for human habitation.

“These incomplete projects don’t just stand as unfinished structures. They are monuments to inefficient management, corruption, lost opportunities, deferred dignity and unfulfilled promises to the public,” said Macpherson.

In March, [we reported](https://groundup.org.za/article/police-minister-reveals-he-has-been-working-from-home-due-to-the-terrible-state-of-saps-telkom-towers-building/) how then police minister Bheki Cele had been working from home for four years due to the state of the Telkom Towers.

About R1-billion has been spent on upgrades over ten years. Yet the building still bears the Telkom sign and costs millions annually in security alone. Out of nine buildings in the complex, only one has ever been occupied by SAPS, leaving R592-million worth of building vacant, a portfolio committee oversight report said.

The committee’s [oversight visit](https://groundup.org.za/article/saps-headless-chicken-approach-to-its-r1-billion-shoddy-national-headquarters/) in October revealed numerous problems. The Department of Labour had found faulty electrical wiring and unmaintained fire extinguishers and air conditioning systems. The committee also noted non-functioning lifts, water damage and flooded parking bays.

Yet a facilities management service provider still holds a contract for maintaining the North Wing, despite the building being unoccupied.

The minister announced that the department is considering either repurposing the complex or removing it from its portfolio entirely.

He also revealed that out of 206 current infrastructure projects, 164 are experiencing delays, costing nearly R3-billion over several financial years.

“These delays are not just figures in a report, they represent stalled progress, halted economic growth, and deferred services for millions of South Africans,” said Macpherson.

On Wednesday the portfolio committee recommended that the minister brief the committee quarterly, submit a report within 30 days on a previous [forensic investigation](https://groundup.org.za/article/public-works-to-investigate-mismanagement-of-the-telkom-towers-complex-used-by-saps/), and initiate a new independent investigation into the procurement and failed refurbishment of the Telkom Towers complex.

The oversight report also noted that the utilisation of the Telkom Towers had been intended to alleviate the pressure on the private lease budget, but instead SAPS continues to pay “excessive amounts” for private leases while government-owned buildings remain unused.

Macpherson announced that contractors who fail to meet their obligations will face immediate consequences, including blacklisting.

![Image](https://groundup.org.za/media/_versions/images/photographers/matthew_hirsch/macpherson_extra_large.jpeg) Public Works and Infrastructure Minister Dean Macpherson revealed on Thursday in Parliament that nearly 80% of public works projects are currently delayed. Photo: Matthew Hirsch

**DM**