title: "South African Firm Moves to Block Eskom Power-Grid Regulations"
description: "A South African power-project developer is seeking to block new rules governing the connection of plants to the national electricity grid, saying they are flawed and will impair the addition of more generation capacity."
type: "NewsArticle"
publisher: "Daily Maverick"
site: "https://www.dailymaverick.co.za"
section: "Newsdeck"
canonical_url: "https://www.dailymaverick.co.za/article/2023-07-21-south-african-firm-moves-to-block-eskom-power-grid-regulations/"
published: "2023-07-21T19:01:37"
lang: "en-ZA"
word_count: 241
---

# South African Firm Moves to Block Eskom Power-Grid Regulations

> A South African power-project developer is seeking to block new rules governing the connection of plants to the national electricity grid, saying they are flawed and will impair the addition of more generation capacity.

Published 21 July 2023, 21:01 SAST

## Key points
- Eskom's attempts to access grid capacity may be "unlawful, unreasonable and irrational" according to one developer, potentially hindering new operations and increasing costs for customers.
- Eskom Holdings SOC Ltd. is struggling to meet electricity demand, resulting in power cuts and economic strain
- G7 Renewable Energies argued that Eskom’s Interim Grid Capacity Allocation Rules will hinder new operations
- The rules will impose greater costs on developers of new generation plants and their customers
- G7 Renewable Energies is involved in two wind farms that are not part of a government program to buy power from producers

## Content

State-owned utility Eskom Holdings SOC Ltd. is struggling to meet electricity demand, resulting in almost daily power cuts that are hobbling economic growth. Private generation projects that could relieve pressure on the system have been sidelined, in part because of a lack of connections to the grid.

To alleviate that pressure, Eskom introduced its so-called Interim Grid Capacity Allocation Rules, but developer G7 Renewable Energies argued they will hinder new operations.

Eskom’s application of the IGCA rules “will determine applications for grid access in accordance with rules which have been adopted in a manner that is unlawful, unreasonable and irrational,” G7 Chief Executive Officer Kilian Hagemann said in a copy of a filed affidavit seen by Bloomberg. The rules will also “compel applicants for access to undertake procedures which are onerous and prejudicial,” he said.

Eskom said it wasn’t immediately able to comment. In June, the utility [said](https://www.bloomberg.com/news/articles/2023-06-26/eskom-latest-generation-improves-off-peak-blackouts-suspended)the rules would avoid “hogging” of grid capacity and ensure only so-called shovel-ready projects are allocated capacity.

The rules will impose greater costs on developers of new generation plants and their customers, the South African Independent Power Producers Association, a lobby group, [said](https://www.bloomberg.com/news/articles/2023-06-26/eskom-latest-generation-improves-off-peak-blackouts-suspended) earlier this month.

G7 Renewable Energies is involved in two wind farms identified in the court papers that are not part of a government program to buy power from producers, but will provide electricity to private customers. Such projects “will serve to reduce the burden on Eskom,” the company said.