The long overdue update was provided in a presentation on Tuesday to Parliament’s Portfolio Committee on Mineral Resources and Energy.
“In March 2021, the department had a backlog of 4,467 applications on the three licensing categories – mining permits, mining rights and permit rights,” it said.
“Currently, the backlog is 2,625 – a 43.5% reduction from the previous backlog report.”
This is not like-for-like: In February 2021, the number stood at 5,326 – but for the DMRE, at least things are moving in the right direction.
More importantly, the DMRE has dropped the tender it issued to replace Samrad, which would have involved a completely unnecessary reinvention of the wheel when off-the shelf cadastral systems were available.
The Minerals Council SA – the main industry grouping – has even offered to help pay for such a system.
“Unsurprisingly, they are having to do a full do-over on the cadastral tender,” Paul Miller, director of consultancy AmaranthCX, told Business Maverick.
“It was clear that the first effort was a disaster waiting to happen … we are supposed to accept that it was pulled because of technical audit findings. Whatever the reason, a do-over was inevitable and should be welcomed.”
The department said in the presentation: “On Sita’s [State Information Technology Agency] advice, informed by their internal and external audit process outcomes”, it had requested the procurement process be halted.
That raises a few questions – but moving right along: The DMRE signalled that it is indeed aiming for an existing cadastral and said in its presentation that it is “benchmarking similar systems in countries that have successfully implemented a cadastral [system]”.
The presentation went on to say that it had done a benchmarking exercise with Namibia, and planned to do another at the end of November with Botswana.
Visit Daily Maverick's home page for more news, analysis and investigations
Director-General Jacob Mbele made a commitment in October to the parliamentary portfolio committee that a cadastre would be procured by the end of the financial year.
“After 10 years in denial, the department has accepted that a custom-designed cadastral system is not viable, and have undertaken to reach financial closure on the purchase of an off-the-shelf system by the end of this financial year,” James Lorimer, DA MP and shadow minister for minerals and energy, told Business Maverick.
“The ANC denied the reality of a failed system for years. After first trying everything else, they’ve now made what could be the correct decision. We can only hope the system they purchase will be transparent and have an extensive track record of success.
“The lack of transparency has provided cover for shady dealing that has badly affected the operations and credibility of our mine licensing system,” Lorimer added.
The critical thing about a mining cadastre is that it brings transparency to the industry. It is an online portal that is open to the public. It provides comprehensive geological data about a country or mining jurisdiction, provides information on mining permits that have been issued, including expiry dates, and lists available mining or prospecting rights and so on.
The application backlog and the lack of a transparent cadastre highlighted the chaotic state of the DMRE while thwarting badly needed investment in the mining sector, notably on the exploration front.
South Africa’s share of global exploration spend has been below 1% for years.
The shambles that is the DMRE was thrown further into sharp relief when Business Maverick reported in October that it had put out a tender for an assessment of its data and phone networks.
The document indicated that the department’s systems were so obsolete that it could no longer source spare parts and that it had not had managed services for almost a decade.
Read more in Daily Maverick: “Mineral Resources and Energy data and phone networks assessment tender reveals the lights may be off and nobody home”
It was also a flashing red light that the department would struggle to manage a custom-designed cadastral network. It simply lacks the capacity. But, hopefully, a functional cadastral system will be up and running next year. DM/BM