South Africa

POWER GENERATION OP-ED

Nuclear power station life-extension project running late, even before it starts

Nuclear power station life-extension project running late, even before it starts
Eskom takes delivery of the first of six steam generators for the Koeberg life extension project. (Photo: Eskom)

Installation of six new steam generators at Eskom’s Koeberg nuclear power station was due to have started on 5 January 2022, but is already running late.

Koeberg power station, on the west coast of South Africa about 35km north of Cape Town, is approaching the end of its 40-year design life and operating licence. However, in 2022 and early 2023, the nuclear power plant is scheduled for several upgrades to extend its operational life for a further 20 years.

This includes the replacement of three steam generators on each of the two 920MW nuclear reactors, as well as replacement of the reactor head, control rod drive mechanism and reactor in-core instrumentation cables on one of the nuclear reactors.

Other work for the life extension involves:

  • Replacement and enlargement of the PTR storage tanks used to store borated water for the reactor cavity and spent fuel cooling system.
  • Repairs, modifications and monitoring of the reactor containment building to include cathodic protection to prevent corrosion of steel reinforcing (rebar) in the concrete.
  • Replacement of the heater elements on the pressurisers.

Other plant modifications and upgrades for reliability and sustainability include transformer replacements, digital system upgrades, security system upgrades, cooling water systems, piping and heat exchangers.

Planning for replacing the six steam generators has been in progress for several years. However, Eskom’s chief nuclear officer, Riedewaan Bakardien, says the impact of the coronavirus pandemic and the Omicron variant, which led to travel restrictions and the implementation of additional protocols, “has proven a challenge in getting some of the required international resources on site in time”.

In the meantime, Eskom says it is finalising the facilities to support the project team during the life extension work. This includes installing and load-testing the large cranes which are critical to the lifting operations of the project.

A further stumbling block is that Eskom’s installation safety case has not yet been approved by the National Nuclear Regulator (NNR) and a green light from the NNR to start work has not been received.

The NNR normally provides its final approval once it has completed detailed reviews of all the major work that would be executed during an outage to ensure nothing is missed in terms of cross-functional impacts. 

“This final approval for plant changes is usually issued a month before the start of an outage,” says Eskom.

The reactor shutdowns at Koeberg for the life extension come at a time of significant electricity supply constraints in South Africa. In 2021, these constraints resulted in a record number of 1,136 hours of load shedding, with an associated loss of some 1,773 gigawatt-hours of electricity to the productive economy.

The life extension of Koeberg nuclear power station will reduce the generation capacity available for duty in South Africa by about 900MW, as the two nuclear reactors are shut down sequentially, each for periods of about five months.

The life extension therefore increases the probability and risk of load shedding during 2022 and the first quarter of 2023, and any time overruns in the planned shutdown periods of either reactor will extend the risk and the consequences of load shedding.

In the unlikely case of extended time-overruns, resulting from serious unforeseen circumstances, the worst-case scenario would be that the life extension project may not be completed by the time the current operating licence expires in 2024.

In this situation, the NNR may require the whole power station (1,840MW) to be shut down until the reactors are safe to restart, after all work is completed and a new operating licence is granted.

Eskom is at pains to point out that while the green light has not yet been received from the NNR to proceed, this is not a cause for concern. Eskom says it is committed to ensuring that all NNR requirements are complied with, even if more work is needed in the last days of preparation. 

Eskom’s safety case for the life extension and steam generator replacement project is being reviewed by the NNR and, according to Bakardien, there have been no new developments arising from the NNR formal review. 

“The NNR has provided Eskom with a positive view of the safety case as the review has progressed, but the final approval is not granted until the NNR is 100% satisfied and all of the issues raised have been resolved,” he adds.

The utility says it is hoping final approvals from the NNR will be received within the next two weeks and the steam generator replacement work will begin in early February 2022. DM

Chris Yelland is managing director of EE Business Intelligence.

Gallery
Absa OBP

Comments - Please in order to comment.

  • Sam Shu says:

    Thanks Chris Yelland for keeping us informed on the power issues in South Africa

  • Nick Miller says:

    Eskom is unable to comply with its statutory obligation on environmental matters, what comfort can anyone have that it will comply with NNR requirements?

  • Fox Bravo.. says:

    To ensure clean power we need to support Eskom with the Koeberg life extension at every front. This life extension will result in many millions of tonnes of coal not being burned. It’s imperative, its good for SA its good for the environment.
    We need more nuclear in South Africa and we need the press to keep an open mind and to support that.

  • Guy Young says:

    The loss of time is significant and and unlikely to be made up. If this is how Eskom starts a project it is more than likely that the whole project will be years behind before it feeds anything into the national grid.

Please peer review 3 community comments before your comment can be posted

We would like our readers to start paying for Daily Maverick...

…but we are not going to force you to. Over 10 million users come to us each month for the news. We have not put it behind a paywall because the truth should not be a luxury.

Instead we ask our readers who can afford to contribute, even a small amount each month, to do so.

If you appreciate it and want to see us keep going then please consider contributing whatever you can.

Support Daily Maverick→
Payment options

Daily Maverick Elections Toolbox

Feeling powerless in politics?

Equip yourself with the tools you need for an informed decision this election. Get the Elections Toolbox with shareable party manifesto guide.