South Africa

MUNICIPAL (DIS)EMPOWERMENT

You knew it all along, Ekurhuleni! Community waste collectors were ‘ripped off’

You knew it all along, Ekurhuleni! Community waste collectors were ‘ripped off’
A waste picker sorts out recyclable material in Ekurhuleni, Gauteng. (Photo: Gallo Images / OJ Koloti)

The City of Ekurhuleni repeatedly dodged claims by amaBhungane that a waste collection programme to empower the city’s poorest, short-changed them instead. But city officials knew all along. Their own investigation, now obtained by amaBhungane, had told them the same thing.

Disgruntled waste collectors in Ekurhuleni, contracted on an ambitious R1.2-billion job creation and empowerment programme, told amaBhungane in July that promises were broken, that they were underpaid and companies supposed to mentor them had pocketed most of the money.

The city dodged the claims then — ignoring repeated questions — and now, confronted by amaBhungane with its own report, the city continues to deny there was anything amiss. 

But the forensic investigation by independent auditors, commissioned by the city itself, gives broad backing to allegations published by amaBhungane — although the report deals only with one of five mentor companies contracted by the city. 

The report was obtained by amaBhungane via a Promotion of Access to Information Act (PAIA) application lodged with the city in which we requested the report by name — after having been tipped off about its existence.  

The investigation raised the same red flags that amaBhungane did — and calculated in detail the substantial sums it said were still owed to community contractors. 

The city received that report three years ago and seemingly chose to brush off its findings.

Our article of 21 July 2021 described how five established local companies were contracted by the city to “mentor” 45 community-based waste collecting contractors and six recyclers to provide comprehensive refuse removal and recycling services across large parts of Ekurhuleni. 

The programme covered five years from 1 July 2016 to 30 June 2021. 

By the end of that time, these small businesses were supposed to have favourable banking profiles, own their plant and equipment, and have the financial muscle and business know-how to go on their own. 

Except, according to the community contractors, that did not happen: the city ignored complaints that the established mentor companies were short-changing them.

AmaBhungane wrote repeated emails to the city requesting information about the project, including under PAIA

Most of the emails were ignored. 

When the report was finally handed over, it revealed that just a third of the way through the contract, a group of community contractors had allegedly been underpaid by R2.69-million, and their “mentor” had allegedly been overpaid R7.6-million for what were described as “fictitious” services.

Arms Audit Forensic Report:

The city would only say that it had “made all payments for services rendered in line with the approved contract”.

Questions from amaBhungane:

The report and what it tells us

In 2018 the city manager, Dr Imogen Mashazi, contracted an outside auditing company to review the performance by one mentoring company — a joint venture by MCC Security Projects and Before Dawn Property Development — in one area, Tembisa. 

The subsequent review is dubbed a “Phase 1 report” but it is not clear whether others were done. If so, they were certainly not disclosed to us. The audit company referred all queries to the city. 

Nevertheless, the contractual problems raised in the report apply to most mentor companies and community contractors.

The 102-page report, dated November 2018 and titled “Review of Possible Non-Compliance with the terms of Contract No. A-WMS 11-2015” was compiled by ARMS-Audit and Risk Management Solutions, a Johannesburg forensic auditing firm that specialises in services to government departments. 

The auditors concluded that the waste collection services the city required were being efficiently delivered — but not with the intended empowerment outcomes.

The theme of the report was that the contractual terms of the programme had resulted in an “unbalanced” power relationship between the “mentors” — known as development contractors (DCs) — and the community-based contractors (CBCs). 

The relationship was not one of sub-contracting an independent entity, but of employment. There was an urgent need for the city to intervene and correct this.

The development contractor (the MCC/Before Dawn joint venture) had also not yet signed the city’s service level agreement. 

And 18 months into the contract, the formal relationship between the development contractor and the community-based contractors remained in an unsigned draft form. 

The report recognised that the community-based contractors lacked the legal skills to enter into such relationships.

“We concluded that the purpose of the contract is not being achieved and this is a result of the power relationship between the Development Contractor and the Community Based Contractor being unbalanced. We recommend that the City of Ekurhuleni assist the Community Based Contractors with legal advice which can be outsourced… for the purpose of contract negotiations.”

The city seems unconcerned about this power imbalance, telling amaBhungane, “The service providers were appointed in different areas with different quantities and rates. The different contracts with the CBCs were in line with the tender requirements. The City had a contractual relationship with the Development Contractor and did not have any direct contractual relationship with the CBCs.”   

The contract made provision for payments to be calculated on the basis of the number of waste collection points serviced. The problem was establishing how many there really were. 

The auditors examined municipal valuation rolls, GIS maps and physical counts by the city’s waste management department. 

Much of the report was a neighbourhood-by-neighbourhood breakdown of stands, yards, tuckshops (which generate a great deal of waste) and other local businesses. 

The report concluded that there were 57,762 formal service points. But the development contractor had claimed for 76,000 formal service points.

“The claims submitted by MCC Security Projects and Before Dawn Property Development CC JV were inflated and it resulted in the overpayment of R7,610,484.00 up to July 2018,” the auditors noted. 

“We recommend that officials at MCC Security Projects and Before Dawn Property Development CC JV be informed of the confirmed Formal “Service Points” and the amount of R7,610,484.00 that was paid for non-existent service points to date and that the money be recovered.”

The city did not do this. 

In response to amaBhungane’s questions, Ekurhuleni spokesperson Zweli Dlamini said, “There was a count of the service points and everything was found to be done in line with the SLA. There was no overpayment but instead the municipality saved money in this regard.”

The city did not explain the discrepancy between the auditor findings and its own, or how it was resolved.

Before Dawn chief executive Velani Magagula, responding on behalf of his joint venture with MCC Security, said he was not aware of the forensic report and was also constrained by a confidentiality clause in his contract with the city.

“The Joint Venture has not seen the 2018 Audit and Risk Management Solution Forensic Investigation… As a result, the Joint Venture is not aware of the alleged R7.6-million overpayment. 

“If this were true, the Joint Venture assumes that it would have been advised to repay the overpayment back, the Contract Cancelled and that it would appear in the City of Ekurhuleni financial statements.” 

Magagula’s full response:

The auditors’ other key finding was that the municipality had oversight over the amount paid to the development contractor, but not over the amount paid to the sub-contractor, which was therefore more arbitrary.

“We concluded that the money paid for the management services by the Development Contractor is fixed and does go to the Development Contractor and  that the money collected for services rendered by the Community Based Contractor is appropriated by the Development Contractor.”

The report’s astonishing conclusion was that over a period of only 17 months, each community-based contractor — averaging a staff of about 14 workers — had been underpaid by R2.69-million.

“We calculated that in the Tembisa area, each Community Based Contractor will be owed R2,690,119.14 ON AVERAGE by the development contractor. The Development Contractor is liable in total (on average) to the Community Based Contractors for an amount of R32,281,429.70… 

“We recommend that the Development Contractor — MCC  Security and Before Dawn JV — be informed that they should provide proof that they have paid the money to the Community Based Contractors.”

The city dodged amaBhungane’s question on this recommendation, noting only that it had “made all payments for services rendered in line with the approved contract”. 

That left unanswered the issue of whether the development contractors had met their obligations to CBCs.

Magagula, on behalf of the development contractor, repeated that he was not aware of the report or any such finding.

“It would have been proper that if there were a forensic report that adversely affected the Joint Venture, that the Joint Venture would have been asked to comment. As a result, the Joint Venture is not aware of the alleged R2,690,119.14 on average owed to each of the Tembisa Community Based Contractors by the Development Contractor.”

He said forensic investigators may not have considered the costs associated with the waste collection services — which the mentor companies were entitled to deduct from their payments to the community-based contractors. 

These included “capital redemptions for plant and vehicles”, fuel and maintenance. 

The investigation report also identified a problem of more ambiguous “informal” service points, often rubbish dumped in places inaccessible to trucks. 

There were contradictions in the definitions of collection points in these areas, no reliable count of the number of shack dwellings or backyard rooms, and no understanding of how many families lived in each. Numbers seemed to fluctuate month by month.

“We established and concluded that as a result of Tembisa residents having “back rooms” that result in more than one family occupying one stand, thus a “Service Point” results in the volume of refuse being very high that has an impact on the Community Based Contractors in that it increases operational costs and reduces the life-span of equipment used.”

In other words, this worked to further disadvantage the CBCs. 

The auditors also recommended that the city look into a previous, similar waste collection contract, and ascertain whether those community-based contractors had been underpaid. If necessary, the report recommended that “civil action” be taken.

There is no indication this has been done — or that the lessons learnt from the 2016 contract have been incorporated into the design of a new five-year contract to be awarded soon.

The city would only say that it had taken note of recommendations to strengthen supervision of the implementation of the contracts and that “supervision and monitoring staff has been included on the approved [council] structure”.

Municipal spokesperson Zweli Dlamini said the report and its recommendations “were dealt with according to our internal systems”.

He said the programme was assessed “on an annual basis to ensure that the goals of the city are achieved and we are satisfied with the progress recorded”.

Magagula said the joint venture filed its own report to the municipality at the close of the project, and three months later had received no adverse comments from city officials. 

“Suffice to say the Joint Venture never received any penalties for service delivery failures as stipulated in the contract document. The Joint Venture is proud to say it fulfilled all its obligations in terms of the spirit of the contract, signed contracts and bid specification.” DM

Gallery

Comments - Please in order to comment.

  • Hermann Funk says:

    I am actually getting sick and tired having to read articles like this on a daily basis. Incompetence, theft, corruption and dishonesty appear to be the best qualifications for a government job.

    • Jane Crankshaw says:

      I agree….the tax and rate payer has been so abused for so long now that we’re become anesthetized to the theft and corruption perpetrated by our Government and Municipalities. It’s no wonder that those keeping the fiscus going want to move to the Western Cape and form their own Independent country!

    • Gerrie Pretorius Pretorius says:

      It’s the only qualification and anc membership helps quite a bit, I guess. Then you are also guaranteed protection from prosecution. And should you be the fall person, you can expect ministers and cabinet members to carry you to jail on their shoulders. You can even expect a medical pardon should the sentence seem too long or unfair.

  • Bryan Shepstone says:

    So much for Ubuntu… or do I misunderstand the concept? 🤔

  • Alley Cat says:

    Robbing Hoods (ANC) Steal from the poor and give to the rich. Would be great if Amabhungane could figure out which cadres received kickbacks from these thieves?
    Keep up the great work and keep digging!

  • hilton smith says:

    keep following the money

  • ethne starke says:

    Viva Western Cape independence. I’m totally “g*atvol” of hearing about the stealing, pillaging and blatant dishonesty.

  • Jacques Wessels says:

    Here we go again and again… This will not stop but to convince one ANC voter in your immediate influence sphere to change to how ever opposition party & DM please add this to your Least We Forget infogram so South Africa can stay aware.

Please peer review 3 community comments before your comment can be posted

X

This article is free to read.

Sign up for free or sign in to continue reading.

Unlike our competitors, we don’t force you to pay to read the news but we do need your email address to make your experience better.


Nearly there! Create a password to finish signing up with us:

Please enter your password or get a sign in link if you’ve forgotten

Open Sesame! Thanks for signing up.

We would like our readers to start paying for Daily Maverick...

…but we are not going to force you to. Over 10 million users come to us each month for the news. We have not put it behind a paywall because the truth should not be a luxury.

Instead we ask our readers who can afford to contribute, even a small amount each month, to do so.

If you appreciate it and want to see us keep going then please consider contributing whatever you can.

Support Daily Maverick→
Payment options

Daily Maverick Elections Toolbox

Feeling powerless in politics?

Equip yourself with the tools you need for an informed decision this election. Get the Elections Toolbox with shareable party manifesto guide.