Business Maverick

BUSINESS MAVERICK

Powering up: Eskom completes Medupi — sort of

Powering up: Eskom completes Medupi — sort of
Medupi Power Station under construction in January 2015. (Photo: Gallo Images / Mail & Guardian / Madelene Cronjé)

That the last unit of Eskom’s first mega-project in 30 years has come onstream is not cause for celebration. Medupi and its evil twin Kusile will be remembered — not for bringing power to South Africa — but for their abject lessons in poor leadership and questionable decision making, not to mention corruption, for which South Africa will pay for decades to come.

Eskom has announced that the construction of the Medupi Power Station in Lephalale, the biggest dry-cooled and most expensive power station in the world, has been completed.

Medupi is a 4,764MW power behemoth whose rampant appetite for coal will increase by 16-million tons a year. 

Completion was announced after unit 1, the last of six generation units of the project, finally attained commercial operation status at the weekend.

The power station is Eskom’s first ‘supercritical plant’ (which technically means it burns cleaner than ordinary power plants) and attaining commercial operation status means the unit now complies with all statutory, safety and legal requirements.

However, commercial operation does not necessarily mean that it is performing optimally, which would assume an energy availability factor, among other things, of 90%. The current uptime is closer to 63.3% for the five units, excluding unit 1. This takes into account the fact that three units have had to be switched off for 75 days each to correct the design defects. And one is currently off.

Bheki Nxumalo, group executive for Eskom’s group capital division, says that work remains to be done. “What remains is the last part of implementing the agreed technical solutions related to the boiler design defects on the balance of plant. Once these repairs are completed during the next 24 months, Medupi will reliably deliver power to the national grid at full capacity, helping increase energy security for the country.” 

The unit was first synchronised to the national grid on 27 August 2019 and reached the full load of 794MW on 5 December the same year. During this testing and optimisation phase, unit 1 began to contribute power to the country’s electricity supply — suggesting that its commercial operation will not miraculously increase South Africa’s power supply and may not dramatically affect load shedding. 

“Unit 1 commercial operation is a historic milestone as it signifies the completion of construction for Medupi Power Station,” Nxumalo says. “This is an investment that will serve generations of the people of South Africa and power the economy for at least the next half-century.”

It should be cause for celebration. But South Africans, weary of persistent load shedding and escalating electricity costs, can be forgiven for their reluctance to applaud. 

The power station comes online seven years after the scheduled date of delivery of 2014 and at almost three times the projected R56-billion price tag. It has been mired in controversy from before the first sod was turned, beginning with the acquisition in 2005 by the ANC’s investment arm, Chancellor House, of a 25% stake in Hitachi Africa. Hitachi Africa returned the favour over time, paying Chancellor House a $1-million success fee and $5-million in “dividends” in connection with the Medupi and Kusile contracts.

Hitachi was responsible for building the boilers at Medupi. It was, and remains, the largest contract signed by Eskom in its 90-year history, but whose shoddy design and workmanship is one reason for the delays.

“In a project of this size, it is normal for the customer — Eskom — to appoint an independent contractor to oversee the engineering, procurement and construction (EPC). This contractor would then appoint sub-contractors for civil works, boiler works, the turbo alternator contract, ash handling, control and instrumentation and so on,” says Chris Yelland, energy expert and MD of EE Publishers. 

The EPC contractor is responsible for ensuring the project is delivered on time, on budget and according to specification. 

However, Eskom allocated the responsibility to Eskom Capital Projects because it believed the fee — usually 10% of project value — to be too expensive. 

“Eskom had not done a big build in over 20 years… it had lost significant engineering and project management skills, yet it chose to take on all of that risk for a 10% saving,” Yelland says. 

To add insult to injury, Eskom Capital Projects has handed an incomplete project to its client, Eskom Generation. “This would not have been acceptable had the contractor been independent,” he adds.

Thanks to megaprojects like Medupi and the half-completed Kusile, Eskom’s debt is now hovering at around R400-billion, a figure that has National Treasury tied up in knots trying to resolve. Eskom’s debt increased from about R30-billion in 2005/6 to close to R500-billion in 2020, but some R80-billion has been repaid. Over the same period, electricity tariffs increased 488% from 2006 to 2017. 

In 2015 Eskom was downgraded to junk status by Standard & Poor. 

As an additional bonus, Medupi will spew 32,000 million tons of carbon dioxide equivalent (this is a unit of measurement) into the air every year. Former M&G journalist Sipho Kings noted that this is “more than 115 other countries emit individually and is about 5% of South Africa’s emissions”.

One of Eskom’s commitments to the World Bank (in exchange for the loan) was that it would install “flue gas desulphurisation plants”, colloquially called “scrubbers”, at Medupi. This limits sulfur dioxide emissions. In terms of the agreement, this was to be completed by 2022.

Eskom has applied for an extension to 2025. However, Yelland does not believe the scrubbers will ever be installed. “Eskom is only entitled to one extension, but these scrubbers will not be built by 2030, which means Medupi will not achieve its environmental performance.”

While South Africa will take decades to recover from the cost inflicted on the economy by these megaprojects, the question should be, “what has been learnt?”

If the government’s current obsession with nuclear power is anything to go by, one hopes the answer is “a lot”. 

“The nuclear industry is infinitely more complex,” says Yelland. “The regulatory and technical requirements are more demanding and the costs are huge. We need to understand the risks involved. South Africa had superb nuclear engineers, physicists and scientists, but now these are skills that are not in abundance.” DM/BM

Gallery

Comments - Please in order to comment.

  • Dr Know says:

    Supercritical in power generation usually refers to the final steam condition, heated beyond the critical point where water phases to steam without boiling at around 220 Bar, resulting in a more efficient steam cycle.

  • Paul Hollick says:

    Eskom have created a route to move enormous amounts of water from Hartbeespoort Dam to Medupi power station to assist with this “scrubbing”.
    Known as the “Mokolo and Crocodile River (West) Water Augmentation Project Phase 2A: Water Transfer Infrastructure”. In most years this will leave Hartbeespoort Dam with very low water levels, affecting the economy and aesthetics of the area.
    We have been fighting this for several years, but all our objections have been overruled.

  • André van Niekerk says:

    “South Africa had superb nuclear engineers, physicists and scientists, but now these are skills that are not in abundance”. Mmm, this is our core problem in the country. Some of those “skills” left – they were encouraged to do so. There are still lots of skills, but hey are not appointed as many are not cadres. The Cuban engineering fiasco is a case in point. Lots of skills in the country – not used due to being not politically expedient, i.e. they probably won’t share the pot around.

  • Evert de Jongh says:

    “Eskom has announced that the construction of the Medupi Power Station in Lephalale, the biggest dry-cooled and most expensive power station in the world, has been completed.”

    The biggest coal-fired power station in the world? Or are coal-fired power stations the only power stations that use dry-cooled technology?

  • Des Clark says:

    The impact of the influence of Chancellor House seems to be forgotten in the “winds of time”. I would really like to understand the influence Chancellor House had on the very poor technical decisions and how much they extracted from these 2 projects.

  • David Hirsch says:

    Um, “32 000 million tons of CO2 equivalent .. 5% of SA emissions” is 10 666 tons per capita pa or 29 tons per person per day. Sloppy. 32 million more likely – 29 kg per per person per day? – seems a bit high.

  • Willie Maree says:

    This article should be forwarded to the Presidency and Luthuli House for their comments. We the taxpayers of SA deserve a proper reaction from the ANC

Please peer review 3 community comments before your comment can be posted

X

This article is free to read.

Sign up for free or sign in to continue reading.

Unlike our competitors, we don’t force you to pay to read the news but we do need your email address to make your experience better.


Nearly there! Create a password to finish signing up with us:

Please enter your password or get a sign in link if you’ve forgotten

Open Sesame! Thanks for signing up.

We would like our readers to start paying for Daily Maverick...

…but we are not going to force you to. Over 10 million users come to us each month for the news. We have not put it behind a paywall because the truth should not be a luxury.

Instead we ask our readers who can afford to contribute, even a small amount each month, to do so.

If you appreciate it and want to see us keep going then please consider contributing whatever you can.

Support Daily Maverick→
Payment options