South Africa

OP-ED

Roll-out of new emergency generation capacity in South Africa increasingly in disarray

Roll-out of new emergency generation capacity in South Africa increasingly in disarray
(Photo: Chris Warde-Jones / Bloomberg via Getty Images)

Following the announcement on 18 March 2021 of preferred bidders for 2,000MW of new emergency generation capacity in South Africa, the ‘non-negotiable’ timelines for both financial closure by end July 2021 and power to the grid by mid to end 2022, are looking increasingly unlikely. In addition, the local content designated by the Department of Trade, Industry and Competition for plant and components procured under this Risk Mitigation Independent Power Producer Procurement programme is proving to be significantly unrealistic.

Chris Yelland is managing director, EE Business Intelligence.

Some 1,220MW or 61% of the 2,000MW of dispatchable generation capacity procured under the Risk Mitigation Independent Power Producer Procurement (RMIPPP) programme is to come from three floating power plants (powerships) and floating storage and regasification units (FSRUs), all leased from Turkish company Karpowership and moored in South African harbours for 20 years.

Already, Karpowership has successfully applied for exemption from the local content designated by the Department of Trade, Industry and Competition (dtic) for ships, in the request for proposals documents of the IPP Office of the Department of Mineral Resources and Energy (DMRE). The powerships, FSRUs and all associated onboard equipment will come fully equipped, with no local content.

Furthermore, the powerships are fuelled via fully imported liquified natural gas arriving from abroad periodically in tankers to fill up the FSRUs. After regasification, the natural gas obtained is piped to fuel the gas engines driving the generators in the powerships.

A legal challenge by an unsuccessful bidder, DNG Energy, is expected to be heard in court from 14 to 16 July 2021, and could put a spanner in the works. DNG Energy claims that the award of preferred bidder status to Karpowership was irregular and corrupt and that DNG Energy, with its land-based gas-to-power offering, should be substituted as preferred bidder in place of Karpowership.

In addition, the decision by the Department of Forestry, Fisheries and the Environment to refuse the applications by all three Karpowership projects for environmental authorisation, and the subsequent internal appeal announced by Karpowership, is also likely to delay financial closure of these projects.

Even if the internal appeal by Karpowership to the environment department succeeds in reversing this decision, it is expected that this would simply trigger legal proceedings in the courts by environmental groups, in further efforts to prevent the projects from proceeding.

Achieving financial closure by the end of July 2021 for the eight projects making up the balance of 780MW of dispatchable generation capacity to be procured under the RMIPPP programme is also looking to be increasingly unlikely.

This 780MW of dispatchable power would comprise 160MW of wind, 1,700MW of solar PV, 640MW of battery storage and 350MW of diesel/gas to power. There are indications that developers and financiers are in discussions with the IPP Office, and that an extension of two months to end September 2021 for financial closure may also be on the cards for these projects.

The local content designation by the dtic for solar PV panels is also in significant disarray.

First, since announcing the eight preferred bidders incorporating some 1,700MW of solar PV within their projects, it has come to light that Hulamin has closed its aluminium extrusion and anodising lines for the frames of the solar PV modules and that the aluminium frames will now have to be fully imported.

Thus, the 65% local content designated by the dti for the aluminium frames cannot be met. The two potential local manufacturers of solar PV modules in South Africa (ARTsolar/LONGi and Seraphim) have since applied for and obtained exemption from the local content designated by the dtic for the solar PV module frames for the RMIPPP programme. Such exemption, however, has not been obtained for Bid Window 5 of the REIPPP programme at this stage.

Second, the ambitious timelines initially proposed for local assembly of solar PV modules for the 1,700MW of solar PV projects of the RMIPPP programme would appear to have been overstated and unrealistic.

In an article by this writer widely published in the media on 20 April 2021, ARTsolar indicated that it would commence local assembly, testing and quality assurance of 540 W, Tier 1 certified, LONGi solar PV modules in August 2021 from a new ARTsolar factory with a capacity of 500MW per year. Solar PV panels would be stockpiled and delivery to project developers would start in the first quarter of 2022.

Latest information from ARTsolar is that it has still not finalised the importation of the machinery for the new factory from the overseas suppliers, because no committed letters of intent or orders have been received by ARTsolar/LONGi from developers yet. This is perhaps not entirely surprising since financial closure has always been envisaged to end July 2021.

ARTsolar now indicates that instead of the new 500MW per year LONGi solar PV module assembly line being up and running by August 2021, it intends to upgrade its existing assembly line in Pinetown to a 200MW per year, Tier 1 certified solar PV module assembly line by January 2022. The new 500MW per year, Tier 1 certified assembly line would then only be ready to supply by March 2022 at the earliest, with all of this subject to committed orders from developers, in time to justify the new facilities.

There is significant disquiet in the industry among the successful developers and their financiers for the RMIPPP programme, as well as potential bidders for Bid Window 5 of the REIPPP programme, about the ability of ARTsolar/LONGi and Seraphim to deliver locally assembled, Tier 1 certified, solar PV modules, meeting the timeframes and volumes required, and with the minimum local content initially designated by the dtic for both anodised aluminium module frames and the solar PV modules themselves.

Discussions are therefore in progress between developers, financiers, ARTsolar/LONGi, Seraphim, the dtic and the IPP Office to obtain a partial exemption from the designated local content requirements of solar PV modules for the RMIPPP programme, and possibly also for Bid Window 5 of the REIPPP programme.

With a partial exemption, a portion of the solar PV modules to meet the 1,700MW of solar PV for the RMIPPP programme would be required to be locally assembled, with the balance allowed to be fully imported.

This, of course, raises some interesting issues in respect of the allocation of locally assembled and imported solar PV modules among the projects of the RMIPPP programme, noting that locally assembled solar PV modules come at a higher price to the project developers, compared with fully imported solar PV modules.

It is also very unlikely that a developer would allow solar PV modules from two independent manufacturers with different product specifications, on a particular solar PV project. The most that a developer may allow on a particular solar PV project is locally assembled, Tier 1 certified, solar PV modules from ARTsolar/LONGi or Seraphim, used with identical, imported modules manufactured by LONGi or Seraphim in China respectively.

This would lock in LONGi and Seraphim solar PV modules for the full requirements of the 1,700MW of solar PV capacity for the RMIPPP programme, which ARTsolar/LONGi and Seraphim would likely consider to be quite appropriate, as it is they who have stuck their necks out with local solar PV module assembly facilities for the RMIPPP and REIPPP programmes ahead.

The significant disarray in which the minerals department’s RMIPPP programme finds itself clearly indicates the silos in which the dtic, environment department, the IPP Office, Eskom, developers, financiers and local manufacturers exist. This points to the need for far more effective communication and engagement among these energy sector participants, in the national interest. DM

Gallery

Comments - Please in order to comment.

  • Gina Schroeder Schroeder says:

    Thanks Chris,

    I for one hope that the Karpower stays sunken and is not implemented.

    Our Government is wonderful at red tape and bureaucracy but nothing else it seems.

    How is dear Mr Mantashe progressing on his 100MW “permits”. The 100kW to 1 MW is mostly impossible to register with Nersa as it is.

    Love it if you could pull together an article on how much Solar C&I space is actually being installed at the moment. Last I have as relatively reliable is 180 – 200 MW in I think 2018 via the old PQRS website and Canadian Solar who had a 150MW target that year.

    Based on industry movements that I am seeing and EPC contractors that are installing over 1 MW a month I would assume we are at least 300MW per annum.

    Does anyone out there have better info?

  • Peter Bartlett says:

    SHOCKING! if you’ll excuse the pun 😂 and were it not so serious, laughable too. And sounds very much like even if the left hand knew there was a right hand there’s even less chance either hand would know what the other needed to do. At best, the sound of one hand clapping 😥 Thanks, as always, for an insightful article.

  • Alley Cat says:

    P-up and brewery come to mind… Just fascinating that Karpowership got an exemption for local content, but not the reset of the potential bidders? HMM, seems the ANC HAVE figured a way to extract trough feed from the sun… What a useless bunch!

  • Ian Hall says:

    I’ve heard that in the earlier REIPP rounds, now that the developers want to refinance their debt, the government is asking for 50% of the upside?! This is a material breach surely, since the developers would’ve modeled the lower finance rate when bidding!? Talk about political risk…

  • William Stucke says:

    How can Solar PV and Wind power be considered “dispatchable”? The sun is shining or it isn’t. The wind is blowing or it isn’t. The operator has no control at all, and cannot supply power when requested. Without storage, intermittent supplies have limited utility.

Please peer review 3 community comments before your comment can be posted

X

This article is free to read.

Sign up for free or sign in to continue reading.

Unlike our competitors, we don’t force you to pay to read the news but we do need your email address to make your experience better.


Nearly there! Create a password to finish signing up with us:

Please enter your password or get a sign in link if you’ve forgotten

Open Sesame! Thanks for signing up.

We would like our readers to start paying for Daily Maverick...

…but we are not going to force you to. Over 10 million users come to us each month for the news. We have not put it behind a paywall because the truth should not be a luxury.

Instead we ask our readers who can afford to contribute, even a small amount each month, to do so.

If you appreciate it and want to see us keep going then please consider contributing whatever you can.

Support Daily Maverick→
Payment options

Daily Maverick Elections Toolbox

Feeling powerless in politics?

Equip yourself with the tools you need for an informed decision this election. Get the Elections Toolbox with shareable party manifesto guide.