Blackouts Cripple South Africa Again as Eskom Stumbles

Power cables from the state run power provider Eskom are seen running through the morning mist in Johannesburg, South Africa, 18 June 2018. The countries only major power supplier has been experiencing power cuts over the past days due to an ongoing wage related strike. As winter takes hold over the country the usage of power has risen partly causing the power outages EPA-EFE/KIM LUDBROOK

South Africa grappled with traffic gridlock and shuttered businesses after the struggling state power utility cut supply for a third day to prevent a total collapse of the grid.

The return to blackouts compounds worries about Eskom Holdings SOC Ltd.’s precarious position and the threat it poses to the economy. It’s also an embarrassment for the ruling African National Congress just three months ahead of national elections. The rand tumbled Monday and government bond yields surged after Eskom suddenly announced sharply widened cuts.

The crisis places President Cyril Ramaphosa, a former labor leader who took power in February last year, in a quandary. He’ll stand no chance of meeting a pledge to revive the flagging economy unless he fixes Eskom, and his hopes of a decisive win in the May 8 vote will be seriously undermined.

“It’s time to treat it like a wartime emergency,’’ said Iraj Abedian, the head of Pan-African Investments and Research Services, who has advised the government on economic policy.

The utility, which blamed poor maintenance for blackouts late last year, said it’s increasingly concerned about ongoing problems at two new coal-fired power stations. The huge Medupi and Kusile plants — already over-budget and years delayed — are also responsible for a debt crisis that has hamstrung the company.

Ramaphosa said last week that Eskom would be split into three as part of plans to rescue the company — an initiative opposed by labor unions, which fear it will lead to privatization and job cuts. The president also pledged financial support for the utility but didn’t specify an amount. Those undertakings will do little to address Eskom’s problems, Moody’s Investors Service said Monday.

Orchestrating a turnaround will probably require job cuts, making Ramaphosa’s task even trickier. Any attempt to reduce staff numbers will infuriate the unions that backed his rise to power and will play a key role in rallying support for the ANC.

Emergency Meeting

Eskom’s board gathered Monday for a six-hour emergency meeting with Public Enterprises Minister Pravin Gordhan and will commission an urgent review of the new plants, the company said. It’s demanding detail on when the projects will be completed and the extent of design and other operational faults.

The two plants “are continuing to show a lack of reliability to contribute meaningfully to Eskom’s generating capacity, which is a serious concern,” Eskom said.

The rand weakened 0.2 percent against the dollar by 1:35 p.m. in Johannesburg, after dropping 1.4 percent Monday. Yields on benchmark government rand bonds rose 3 basis points to 8.81 percent.

Read: Eskom’s Financial Woes Deepen as New Plant Repair Bill Mounts

South Africans are already familiar with the day-to-day implications of rolling blackouts, after Eskom implemented cuts in 2008, and again in 2015. Load shedding, as the outages are known locally, mean stocking up on candles, wifi disruptions and lengthy commutes on gridlocked roads through blank traffic lights. Many businesses already own costly-to-run diesel generators from the last round of cuts.

The blackouts Monday, when Eskom took 4,000 megawatts of demand off the system, were announced after seven generating units tripped within five hours, the company said. While some were back online by Tuesday, the utility announced another 3,000 megawatts of cuts that will last until 11 p.m.

Two of the generating units that failed on Monday were at Medupi, the Johannesburg-based Business Day newspaper reported, without saying where it got the information. Gordhan said in December that South Africa plans to take action over “sub-standard” work by contractors at Medupi and Kusile, including Hitachi Power Africa Ltd., that were contributing to scheduled blackouts. DM

Gallery

Please peer review 3 community comments before your comment can be posted

We would like our readers to start paying for Daily Maverick...

…but we are not going to force you to. Over 10 million users come to us each month for the news. We have not put it behind a paywall because the truth should not be a luxury.

Instead we ask our readers who can afford to contribute, even a small amount each month, to do so.

If you appreciate it and want to see us keep going then please consider contributing whatever you can.

Support Daily Maverick→
Payment options

Become a Maverick Insider

This could have been a paywall

On another site this would have been a paywall. Maverick Insider keeps our content free for all.

Become an Insider

Every seed of hope will one day sprout.

South African citizens throughout the country are standing up for our human rights. Stay informed, connected and inspired by our weekly FREE Maverick Citizen newsletter.